esolution Design team rectifies the design of hotel building in Jeddah

The hotel complicated design has been awarded to esolution to review the original design, esolution design team findings on the foundations was very critical due to overlooked designed building weight using different software that made the error during design, however the foundation been cast already before esolution design team to be involved into the review work.

Esolution design team in Dubai suggested reduction of total building weight that has been successful to approach before construction happens for first slab in the structure.

Esolution designed all building elements includes precast concrete works and its connection details with the use of building information modeling, esolution developed a structure design model for the tower and that made coordination work easy for all other parties